Construction on Portland

You may have noticed the construction signs appearing on Portland Avenue near the neighborhood. The contractor has provided an update.

They hoped to start April 28th, but they are not exactly certain how this intermittent rain will affect the project.  They are replacing the curbs and driveways over the next 3 weeks or so.  While that is being done, they will have to place traffic into either Northbound only or Southbound only depending on which side of the road they are working.  

Once the concrete work is completed, then the asphalt milling and overlay will follow. They will also be adjusting several manholes that are located in the street.  The traffic will also be one-way traffic during this process and should take 3-4 weeks (pending weather). 